The Effect of Work Time and Cost Control on Project Cash Flow Through Achieving Profit Target in The Construction of The Jenelata Dam Pt. Adhi Karya (Persero) TBK

Authors

  • Rudddin Sekolah Tinggi Ilmu Ekonomi Makassar Bongaya, Indonesia
  • Jannati Tangngisalu2 Sekolah Tinggi Ilmu Ekonomi Makassar Bongaya, Indonesia
  • Syamsul Alam Sekolah Tinggi Ilmu Ekonomi Makassar Bongaya, Indonesia

DOI:

https://doi.org/10.55681/economina.v5i10.4592

Abstract

This study aims to examine and analyze the effect of work time and cost control on project cash flow through the achievement of profit targets in the Jenelata Dam Construction of PT Adhi Karya (Persero) Tbk. The study used a quantitative approach with 49 respondents. Data were collected through questionnaires using a Likert scale and analyzed using the Structural Equation Modeling–Partial Least Squares (SEM- PLS) method using SmartPLS. The results showed that work time had a negative and insignificant effect on project cash flow, while cost control had a positive and significant effect on project cash flow. Achieving profit targets had a positive and significant effect on project cash flow. Work time and cost control each had a positive and significant effect on achieving profit targets. However, achieving profit targets was unable to mediate the effect of work time on project cash flow or the effect of cost control on project cash flow. These findings indicate that cost control and achieving profit targets play an important role in maintaining project cash flow conditions, while work time plays a more important role in supporting the achievement of profit targets than directly affecting project cash flow.

Downloads

Download data is not yet available.

References

Abdul-Rahman, H., Takim, R., & Min, W. (2009). Financial-related causes contributing to project delays. Journal of Retail & Leisure Property, 8, 225–238. https://doi.org/10.1057/rlp.2009.11

Abotaleb, I. S., El Sawaf, N. M., Abdel Aziz, M. H., & El Gohary, K. M. (2024). Investigation of critical factors affecting cost overruns and delays in mega construction projects. Alexandria Engineering Journal, 93, 300–325. https://doi.org/10.1016/j.aej.2024.03.019

Al Alawi, M. (2021). Delay in payment effects on productivity of small and medium construction companies in Oman: Exploration and ranking. Asian Journal of Civil Engineering, 22, 1347–1359. https://doi.org/10.1007/s42107-021-00387-8

Brigham, E. F., & Houston, J. F. (2021). Fundamentals of financial management (16th ed.). Cengage.

Creswell, J. W. (2014). Research design: Qualitative, quantitative, and mixed methods approaches (4th ed.). SAGE Publications.

Datar, S. M., & Rajan, M. V. (2018). Horngren’s cost accounting: A managerial emphasis (16th ed.). Pearson.

Elserougy, M., Khodeir, L.M., & Fathy, F. (2024). Practices and techniques for construction projects cost control: A critical review. HBRC Journal, 20(1), 525–552. https://doi.org/10.1080/16874048.2024.2337060

Franklin, M., Graybeal, P., & Cooper, D. (2019). Principles of accounting, volume 2: Managerial accounting. OpenStax, Rice University.

Fransiska, & Fahmi, A. (2017). The role of project cost budgets as a cost control tool in achieving company profit targets. Journal of Accounting Science, 5(1), 39–44. https://doi.org/10.37641/jiakes.v5i1.16

Ghozali, I., & Kusumadewi, KA (2023). Partial least squares: Concepts, techniques, and applications using the SmartPLS 4.0 program for empirical research. Diponegoro University Publishing Agency.

Hair, JF, Babin, BJ, Anderson, RE, & Black, W.C. (2019). Multivariate data analysis (8th ed.). Cengage.

Husen, A. (2011). Project management: Planning, scheduling, and project control (2nd ed.). Andi.

Ilham, M., Akob, M., & Sumail, LO (2025). The impact of project work time on cash flow: Sales targets and profit targets as mediating variables. Jambura Economic Education Journal, 7(1), 75–97. https://doi.org/10.37479/jej.v7i1.25252

Kerzner, H. (2022). Project management: A systems approach to planning, scheduling, and controlling (13th ed.). Wiley.

Khan, Z. A., & Saeed, A. (2024). Integrated agent-based simulation and game theory decision support framework for cash flow and payment management in construction projects. Sustainability, 16(1), 244. https://doi.org/10.3390/su16010244

Kim, B., Reinschmidt, K. F., & Kim, H. (2019). Investigating profitability performance of construction projects using big data: A project analytic approach. Journal of Building Engineering, 26, 100850. https://doi.org/10.1016/j.jobe.2019.100850

Park, H. K. (2004). Cash flow forecasting in construction project. KSCE Journal of Civil Engineering, 8(3), 265–271. https://doi.org/10.1007/BF02836008

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) – Seventh edition and the standard for project management. Project Management Institute.

Rajabi, R., & Haji Yakhchali, S. (2025). Optimizing cash flow in construction portfolios: A metaheuristic approach from the organization’s perspective. Ain Shams Engineering Journal, 16(2), Article 103259. https://doi.org/10.1016/j.asej.2024.103259

Sekaran, U., & Bougie, R. (2016). Research methods for business: A skill-building approach (7th ed.). John Wiley & Sons.

Sugiyono. (2022). Quantitative research methods. Alphabet.

Tsai, K.-H., Hsieh, T.-Y., & Peng, Y.-C. (2021). Construction cash flow risk index. Journal of Risk and Financial Management, 14(6), 269. https://doi.org/10.3390/jrfm14060269

Downloads

Published

2026-10-30

How to Cite

Rudddin, R., Tangngisalu2, J., & Alam, S. (2026). The Effect of Work Time and Cost Control on Project Cash Flow Through Achieving Profit Target in The Construction of The Jenelata Dam Pt. Adhi Karya (Persero) TBK. JURNAL ECONOMINA, 5(10), 7930–7942. https://doi.org/10.55681/economina.v5i10.4592