An Adaptive Risk Management Strategy Model for the Successful Implementation of the Bhayangkara 1-Graha Raya-Pondok Serut-Kayu Gede 1-Kayu Gede 2 Road Improvement Project

Authors

  • Titi Siti Masturoh Universitas Mercu Buana, Indonesia
  • Muhammad Isradi Universitas Mercu Buana, Indonesia
  • Mawardi Amin Universitas Mercu Buana, Indonesia

DOI:

https://doi.org/10.55681/armada.v4i9.3959

Keywords:

Adaptive Risk Management Strategy, Project Success, Road Improvement Project, Project Environment, Construction Equipment, SEM-PLS

Abstract

This study aims to develop an adaptive risk management strategy model to improve the success of the Bhayangkara 1 – Graha Raya – Pondok Serut – Kayu Gede 1 – Kayu Gede 2 Road Improvement Project. The study employs a quantitative approach using a survey method. Data were collected through questionnaires distributed to project personnel and analyzed using Structural Equation Modeling–Partial Least Squares (SEM-PLS) and Importance Performance Map Analysis (IPMA). The variables examined include project environmental conditions, human resources, construction equipment, adaptive risk management strategy, and project success. The findings indicate that project environmental conditions and construction equipment have a positive and significant effect on adaptive risk management strategy, while human resources do not show a significant effect. Furthermore, adaptive risk management strategy has a positive and significant influence on project success, particularly in achieving project objectives related to cost, time, and quality. The study concludes that implementing an adaptive risk management strategy supported by a conducive project environment and adequate construction equipment is essential for enhancing the success of road improvement projects.

Downloads

Download data is not yet available.

References

Abdallah, A., Doloi, H., & Holzer, D. (2025). Exploring contextual issues impacting delivery and performance of public sector construction projects in Tanzania. Built Environment Project and Asset Management, 15(2), 228–246. https://doi.org/10.1108/BEPAM-03-2024-0068

Abdulwahab, A., Babatunde Isa, R., & Opeyemi Bello, A. (2023). Barriers to Adoption of BIM-Based Risk Management in the Construction Industry: A Systematic Literature Review and Bibliometric Analysis. July. https://www.isarconference.org/

Agusman, Prasetya, H. B., & Purba, H. H. (2021). Tinjauan dan analisis risiko dalam proyek konstruksi bangunan: Studi literatur. Jurnal Teknologi Dan Manajemen, 19(2), 41–52. https://doi.org/10.52330/jtm.v19i2.29

Ahp, M. M. (2023). Evaluasi manajemen risiko proyek konstruksi terhadap biaya operasional proyek menggunakan metode ahp. 6(2), 215–224. https://doi.org/10.22219/jaa.v6i2.26571

Alkilani, S., & Loosemore, M. (2022). Project performance measurement for small-and-medium sized construction contractors in the Jordanian construction industry. Construction Management and Economics, 40(10), 743–769. https://doi.org/10.1080/01446193.2022.2108863

Ayu, E. S., Khaidir, I., & Rita, E. (2024). Kajian pengaruh manajemen sumber daya terhadap produktivitas pelaksanaan proyek konstruksi gedung. Siklus: Jurnal Teknik Sipil, 10(1), 80–90. https://doi.org/10.31849/siklus.v10i1.11534

Bello, A. B. (2025). Adaptive Project Management Strategies for Complex , Multi-Stakeholder Environments : Balancing Agility , Risk , and Strategic Alignment Effectively. 14(02), 240–254. https://doi.org/10.7753/IJCATR1402.1017

Davidov, P., Ainbinder, I., Ayoubi, N., Avivi, B., & Eliyahu, L. (2023). Implementation of Project Management Knowledge Areas by Project Managers. 13(2), 138–147. https://doi.org/10.32738/JEPPM-2023-0014

Dewi, R., Soemardi, B. W., & Waty, M. (2025). Analisis tantangan dan pengelolaan risiko proyek pembangunan Ibu Kota Nusantara dengan pendekatan kualitatif. Media Ilmiah Teknik Sipil, 13(1), 1–8. https://doi.org/10.33084/mits.v13i1.8660

Dina, D. M., & Amin, M. (2025). The Effect Of Toll Road SPM Service Substance On Toll Road User Satisfaction In The Jabodetabek Area). Jurnal Infrastruktur, 9(1), 7–14.

Ervianto, W. I. (2023). Manajemen proyek konstruksi. Andi.

Hair, J. F., Black, W. C., Babin, B. J., & Anderson, R. E. (2021). Multivariate Data Analysis (8th ed.). Cengage.

Hair, J. F., Hult, G. T. M., Ringle, C., & Sarstedt, M. (2022). A primer on Partial Least Squares Structural Equation Modeling (PLS-SEM). Sage Publications.

Hillson, D. (2024). Managing project risk. In The Handbook of Project Management (pp. 213–229). Routledge. https://doi.org/10.4324/9781003274179-18

Iskandar, D. (2025). Analisa faktor-faktor yang mempengaruhi risiko kegagalan proyek pada pembangunan gedung di Tangerang menggunakan metode SEM PLS dan IPMA. In Skripsi. Universitas Mercu Buana Jakarta.

Ismail, W. N. W., Adnan, H., Azmi, W. F. W. M., Yusop, N., & Isa, S. S. M. (2023). Factors contributing to delay of interim payment in civil engineering projects. International Journal of Technology, 14(4), 867. https://doi.org/10.14716/ijtech.v14i4.3370

Isradi, M., Diaz Nareswari, N., Rifai, A. I., Mufhidin, A., & Prasetijo, J. (2021). Performance Analysis of Road Section and Unsignalized Intersections in Order to Prevent Traffic Jams on Jl H. Djole-Jl. Pasar Lama. INTERNATIONAL JOURNAL OF CIVIL ENGINEERING, 6(1). http://adri.journal.or.id/index.php/aijce/index

Kementerian PU RI. (2023). Kementerian PUPR berkomitmen melakukan pembangunan infrastruktur yang dibutuhkan masyarakat. Kementerian Pekerjaan Umum Republik Indonesia.

Kerzner, H. (2023). Project based problem solving and decision making. John Wiley & Sons.

Love, P. E. D., Matthews, J., & Fang, W. (2021). Reflections on the risk and uncertainty of rework in construction. Journal of Construction Engineering and Management, 147(4). https://doi.org/10.1061/(ASCE)CO.1943-7862.0002030

Memon, A. H., Memon, A. Q., & Khahro, S. H. (2023). Investigation of Project Delays : Towards a Sustainable Construction Industry. 1–17.

Muntu, D., Setyawati, R., Riantini, L. S., & Ichsan, M. (2021). Effect of human resources management and advances to improve construction project performance. Physics and Chemistry of the Earth, 122(January), 103000. https://doi.org/10.1016/j.pce.2021.103000

Nahid, O. F., Rahmatullah, R., Al-Arafat, M., Enamul Kabir, M., & Dasgupta, A. (2025). Risk mitigation strategies in large scale infrastructure project: A project management perspective. SSRN Electronic Journal. https://doi.org/10.2139/ssrn.5113733

Nelsi, M., Abidin, A. Z., & Rostikawati, D. (2021). Pengaruh motivasi dan lingkungan kerja terhadap kinerja pegawai pada Balai Besar Pelaksanaan Jalan Nasional VI Jakarta. Jurnal Tadbir Peradaban, 1(2), 86–95. https://doi.org/10.55182/jtp.v1i2.43

Okudan, O., Budayan, C., & Dikmen, I. (2021). A knowledge-based risk management tool for construction projects using case-based reasoning. Expert Systems with Applications, 173, 114776. https://doi.org/10.1016/j.eswa.2021.114776

PMI. (2021). A guide to the project management body of knowledge (PMBOK® Guide). Project Management Institute.

Prasasto, A. R., & Putra, I. N. D. P. (2024). Analisis pengaruh faktor komunikasi terhadap faktor risiko pada proyek konstruksi gedung bertingkat. Al Qalam: Jurnal Ilmiah Keagamaan Dan Kemasyarakatan, 18(5), 3812. https://doi.org/10.35931/aq.v18i5.3937

Pribadi, T. E. (2024). Analisis pengaruh sertifikasi kompetensi, pengalaman kerja, dan motivasi kerja terhadap kinerja menggunakan metode SEM-PLS IPMA dalam pelaksanaan proyek konstruksi. In Skripsi. Universitas Mercu Buana Jakarta.

Purushothaman, M. B., San Pedro, L. N. R., & GhaffarianHoseini, A. (2026). Construction projects: Interactions of the causes of delays. Smart and Sustainable Built Environment, 15(2), 439–471. https://doi.org/10.1108/SASBE-11-2023-0334

Rafki, D., & Jumas, D. Y. (2024). Civil Engineering Collaboration. 9, 6–7. https://doi.org/10.35134/jcivil.v9i2.72

Rafki, D., Jumas, D. Y., & Heldi. (2024). Analisis faktor yang mempengaruhi kinerja pelaksanaan proyek terhadap kualitas konstruksi jalan nasional di Provinsi Sumatera Barat. Civil Engineering Collaboration, 9(2), 1–6. https://doi.org/10.35134/jcivil.v9i2.72

Sarstedt, M., Richter, N. F., Hauff, S., & Ringle, C. M. (2024). Combined importance–performance map analysis (cIPMA) in partial least squares structural equation modeling (PLS–SEM): A SmartPLS 4 tutorial. Journal of Marketing Analytics, 12(4), 746–760. https://doi.org/10.1057/s41270-024-00325-y

SNI ISO 31000 : 2018 Manajemen Resiko. (2018). SNI ISO 31000 : 2018 Manajemen Resiko. 1–46. https://pu.go.id/pustaka/biblio/sni-iso-31000-2018-manajemen-resiko/BKB99K

Stringer, Jusmidah, Fikri, M., & Nurhidayah. (2025). Analisis persepsi penerapan manajemen proyek terhadap keberhasilan suatu proyek konstruksi. Jurnal Ilmiah Ecosystem, 25(1), 185–195. https://doi.org/10.35965/eco.v25i1.5869

Sugiyono. (2021). Metode Penelitian Kuantitatif, Kualitatif, dan R&D. Alfabeta.

Syahrani, S. A., & Diyanty, V. (2023). Evaluasi manajemen risiko proyek konstruksi terhadap biaya operasional proyek menggunakan metode AHP. Jurnal Akademi Akuntansi, 6(2), 215–224. https://doi.org/10.22219/jaa.v6i2.26571

Downloads

Published

2026-09-30

How to Cite

Titi Siti Masturoh, Muhammad Isradi, & Mawardi Amin. (2026). An Adaptive Risk Management Strategy Model for the Successful Implementation of the Bhayangkara 1-Graha Raya-Pondok Serut-Kayu Gede 1-Kayu Gede 2 Road Improvement Project. ARMADA : Jurnal Penelitian Multidisiplin, 4(9), 5503–5512. https://doi.org/10.55681/armada.v4i9.3959